Labour Day Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMI-SP Exam Dumps - PMI Scheduling Professional

Question # 4

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

A.

Push technique

B.

Many-to-many

C.

One-to-one

D.

Pull technique

Full Access
Question # 5

Which of the following is an output of the Identify Stakeholders process?

A.

Scope baseline

B.

Project scope statement

C.

Project charter

D.

Stakeholder register

Full Access
Question # 6

All of the following statements about the critical path are false except for which one?

A.

The critical path cannot be crashed.

B.

The critical path is the shortest path in the project network diagram.

C.

The critical path is always one path with the longest duration.

D.

The critical path shows the project's earliest date for completion.

Full Access
Question # 7

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your schedule variance for this project?

A.

$11,667

B.

1.02

C.

$7,000

D.

$-111,750

Full Access
Question # 8

Once the project's WBS has been created what process may happen next?

A.

Estimate activity resources

B.

Define activities

C.

Estimate activity durations

D.

Sequence activities

Full Access
Question # 9

Andy is the project manager of the NHGQ project for his organization. He has elected to use a three-point estimate for his project. His project team, however, is complaining about participating in this estimate type because of the time it takes to predict the duration of activities. Andy, as the project manager, tells the project team that they must create the time estimate, as it will help this project and future similar projects. What is a three-point estimate?

A.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration.

B.

Each activity must be estimated for its optimistic, pessimistic, and most likely duration and then an average for the estimate is created.

C.

A three-point estimate, also known as PERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

D.

A three-point estimate, also known as GERT, uses the formula optimistic, plus four times the most likely, plus the pessimistic. This value is then divided by six.

Full Access
Question # 10

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

A.

Contract

B.

Reserve analysis

C.

Scope baseline

D.

Project schedule

Full Access
Question # 11

George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?

A.

.96

B.

-$77,800

C.

$-34,500

D.

-$13,800

Full Access
Question # 12

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

A.

It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

B.

It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

C.

It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

D.

It is a term used to describe activities that are core project management processes, but not core project activities.

Full Access
Question # 13

You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your project. How often should the report be created?

A.

Weekly

B.

One per status milestone reached

C.

Regularly or on an exception basis

D.

Exception-by-exception basis

Full Access
Question # 14

You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?

A.

To understand the exact type of work the project team will be completing

B.

To help the activity go faster

C.

To get better and more accurate results through the decomposition

D.

To create assignments for the project team as the activities are discussed

Full Access
Question # 15

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day of early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

A.

Adding leads to the project work

B.

Fast tracking

C.

Crashing

D.

Using the critical chain method

Full Access
Question # 16

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

A.

It is a report that details the current status of risks and issues.

B.

It is a software application that allows stakeholders to view the project manager's performance.

C.

It is a web-based tool to inspect the project deliverables for performance.

D.

It is a report that reflects the overall performance of scope, schedule, quality, cost, or other project performance metrics.

Full Access
Question # 17

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

A.

Diane

B.

Project sponsor

C.

Risk owner

D.

Subject matter expert

Full Access
Question # 18

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Full Access
Question # 19

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

A.

One

B.

Five

C.

Four

D.

Zero

Full Access
Question # 20

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

A.

Quality inspections and compliance

B.

Location, logistics, and resource availability analysis

C.

Labor productivity studies from previous similar projects in the area

D.

The average price of general labor in the area

Full Access
Question # 21

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Full Access
Question # 22

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

A.

-$75,500

B.

-$390,000

C.

-$487,500

D.

-$65,000

Full Access
Question # 23

You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?

A.

(O+ML+P)

B.

(O+(6M)+P)6

C.

(O+ML+P)/3

D.

(O+(4M)+P)/6

Full Access
Question # 24

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

A.

1.02

B.

0.98

C.

0.90

D.

-$108,120

Full Access
Question # 25

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

A.

Cost variance report

B.

Exceptions report

C.

Performance management report

D.

Schedule variance report

Full Access
Question # 26

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

A.

It means the largest schedule variance you can have is five percent.

B.

It is the earned value divided by the planned value for your project.

C.

It is the expectation of management to be 95 on schedule at 95 percent of the project.

D.

It means you will need to earn at least 95 cents per dollar invested in the project.

Full Access
Question # 27

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is this project's to-complete performance index based on the current BAC?

A.

1.02

B.

0.010

C.

0.75

D.

0.95

Full Access
Question # 28

Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?

A.

140

B.

10

C.

325

D.

5

Full Access
Question # 29

John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:

What is the cost performance index (CPI) of the project at the current point of time?

A.

0.96

B.

1.082

C.

0.833

D.

1.0625

Full Access
Question # 30

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?

A.

Parametric estimate

B.

Definitive estimate

C.

Analogous estimate

D.

Bottom-up estimate

Full Access
Question # 31

Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk-adverse with this project. Which of the following methods should Ben avoid to recoup the project time?

A.

Crashing

B.

Fast tracking

C.

Critical chain methodology

D.

Adding lead time

Full Access
Question # 32

You are the project manager for your organization. You need the oak cabinets for your project delivered by December 1 in order to install the floors around the oak cabinets by December 15. Your company's procurement office generally takes 45 days to complete procurement orders. Based on this information, how should you schedule the lead time for the cabinet delivery?

A.

Cabinet procurement December 1, plus 45 days lead time

B.

Cabinet procurement November 15

C.

Cabinet procurement December 1, minus 45 days lead time

D.

Cabinet procurement December 15 minus 45 days lead time

Full Access
Question # 33

Which of the following provides a method to track project progress during project execution against what was planned?

A.

Team members profile

B.

Benefit-cost ratio

C.

Schedule baseline

D.

Detailed project budget

Full Access
Question # 34

You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

A.

Schedule data

B.

Work performance information

C.

Project management plan

D.

Project schedule

Full Access
Question # 35

Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?

A.

Expert judgment

B.

Analogous estimate

C.

Templates

D.

Parametric estimate

Full Access
Question # 36

Which of the following allows activities to be done in parallel that would normally be done in sequence?

A.

Lag time

B.

Lead time

C.

Fast tracking

D.

Crashing

Full Access
Question # 37

The figure given below demonstrates the communications model for a project. What role does component C play in the communication model?

A.

Encoder

B.

Transporter

C.

Sender

D.

Medium

Full Access
Question # 38

Frank is the project manager of a construction project. In this project, Frank has elected to allow the interior design phase of the project to overlap with the pool construction phase of the project. Normally, Frank would not allow these two phases to overlap, but for this project, he has elected to do so in order to compress the project schedule. What is this schedule compression technique called?

A.

Resource leveling heuristic

B.

Lead time

C.

Fast tracking

D.

Crashing

Full Access
Question # 39

Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

A.

Quality Assurance

B.

Project Plan Development

C.

Integrated Change Control

D.

Project Plan Execution

Full Access
Question # 40

You work as a project manager for BlueWell Inc. You must communicate on a regular basis with all of your project stakeholders. In your project, you have 755 stakeholders. How many communication channels exist in the project?

A.

284,635

B.

570,025

C.

569,270

D.

755

Full Access
Question # 41

You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

A.

Scope change control

B.

Schedule change control

C.

Integrated change control

D.

Change Control Board approval process

Full Access
Question # 42

You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance information to management. All of the following are example of work performance information you should include in your report except for which one?

A.

How the project is performing on its schedule.

B.

Performance of the selected project vendors

C.

Which activities have been started and which activities have been finished.

D.

Percent of completion for the in-progress activities

Full Access
Question # 43

Complete this sentence:

_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.

A.

Corrective action

B.

Report performance

C.

Earned value management

D.

Monitor and control project performance

Full Access
Question # 44

What project management plan will document the time frame and frequency for the distribution of required information?

A.

Scope Management Plan

B.

Communications Management Plan

C.

Stakeholder Management Plan

D.

Schedule Management Plan

Full Access
Question # 45

What is the formula to find the schedule performance index?

A.

EV-PV

B.

EV/AC

C.

EV/PV

D.

EV-AC

Full Access
Question # 46

Your organization wants to start a new project. The study shows that the new project will save organization approximately $200,000 per year. Now it is required to move forward with the project. Which of the following documents will define the project justification?

A.

Feasibility study

B.

Project charter

C.

Work breakdown structure

D.

Project scope

Full Access
Question # 47

You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?

A.

Project calendar

B.

Project constraints

C.

Project objectives

D.

Project management plan

Full Access
Question # 48

Which of the following statements best describes an activity in a project?

A.

It is a defined set of functions a resource must complete for the project scope to be considered complete.

B.

It is the effort needed to complete a work package.

C.

It is the unit of resource utilization needed to complete a project deliverable.

D.

It is a listing of all project work that must be accomplished for the project scope to be considered complete.

Full Access