Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CCM Exam Dumps - Certified Contract Manager

Searching for workable clues to ace the FIDIC CCM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CCM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 17

(Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

A.

The Contractor shall obtain the Engineer’s and the Employer’s prior consent to all Subcontractors.

B.

If no maximum allowable accumulated value of work subcontracted is stated in the Contract Data, the Contractor shall not be entitled to subcontract the whole of the Works without prior consent of the Engineer.

C.

The Contractor shall not be responsible for the acts or defaults of any Subcontractor.

D.

The Contract Data may identify parts of the Works which the Contractor is not entitled to subcontract.

Full Access
Question # 18

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

A.

True

B.

False

Full Access
Question # 19

The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP ' s)?

A.

GP 3

B.

GP 1

C.

GP 2

D.

GPA

Full Access
Question # 20

You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

A.

Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.

B.

Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.

C.

Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.

D.

None of the above.

Full Access
Question # 21

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

A.

True

B.

False

Full Access
Question # 22

If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?

A.

If the defects do not affect the use of the Works for their intended purpose, the Engineer can issue the Taking-Over Certificate.

B.

By giving reasons, the Engineer can refuse to accept the Works until repeated tests have been successfully performed.

C.

The Employer can request to take over the Works.

D.

The Party which is not liable for the cost of rectifying defects can expect the other Party to pay the cost of performing the repeated tests.

Full Access
Question # 23

In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?

A.

True

B.

False

Full Access
Question # 24

(Regarding the FIDIC Red Book (edition 2017): what two answers provide for requirements regarding a notice and other communication?

Choose all of the correct answers (multiple possibilities).)

A.

If a form of communication is to qualify as a Notice, it must be identified as a notice.

B.

If the recipient ' s address differs from the address stated in the Contract Data, notices and other communications may be delivered to that other correct address.

C.

If a form of communication does not qualify as a notice but as other communication, it must be identified as such and shall include reference of provision of Contract under which it is issued (if appropriate).

D.

Notices and other communications shall be delivered to the address of the Contractor ' s Representative.

Full Access
Go to page: