Question # 4

Which statement is valid regarding networks?

A.

A network activity can be assigned to several WBS elements

B.

Material components can be assigned to activity elements

C.

Relationships can be used to connect activities of different networks

D.

A network can be activity-account-assigned and header-account-assigned

Full Access
Question # 5

Which report can use user-specific layouts?

A.

Line item report

B.

Enhanced individual overview

C.

Cost element report

D.

Hierarchical report

Full Access
Question # 6

When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

A.

Service specification

B.

Overall limit (maximum value of all unplanned services)

C.

Service purchase order number

D.

Material master within service specification

E.

Vendor

Full Access
Question # 7

What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question

A.

Location

B.

Material

C.

Production version

D.

Resource

Full Access
Question # 8

Which object is used to allocate the costs from a claim to the project structure?

A.

Network activity

B.

Internal order

C.

Claim

D.

WBS element

Full Access
Question # 9

Revenues & Payment

Your customer wants to plans and post revenues for WBS elements.

What is crucial for the implementation of revenues planning and posting for WBS elements?.

A.

At least one WBS element must be a billing element.

B.

The indicator "Project type" must be set to "Customer project".

C.

Revenue planning and billing must be activated in the corresponding network type.

D.

A sales order item has to be assigned to each WBS element used for revenue planning.

Full Access
Question # 10

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

A.

You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"

B.

You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"

C.

You can always maintain the actual start and finish date of a WBS element

D.

You can only maintain the actual start of a WBS element if the finish date is not maintained

Full Access
Question # 11

The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

A.

Calculation of actual values

B.

Goods receipt for purchase order

C.

Creation of purchase orders

D.

Activity allocation

Full Access
Question # 12

How can you update the degree of processing for an activity?

A.

By using results analysis

B.

By changing the activity

C.

By scheduling the activity

D.

By confirming the activity

Full Access
Question # 13

Where do you control whether a project stock is managed as valuated or non-valuated project stock?

A.

In the network activity

B.

In the project definition

C.

In the WBS element

D.

In the material master

Full Access
Question # 14

Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

A.

Structure overview for budgets

B.

Hierarchical report on budget updates

C.

Cost element report on budget updates

D.

Line item report for budgets

Full Access
Question # 15

You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

A.

Maintain subordinate internal activity elements assigned to other work centres

B.

Increase the capacities of the work center in the project planning board.

C.

Trigger automatic capacity leveling inside the project planning board

D.

Shift activities backward or forward on the time axis where more capacities are available

Full Access
Question # 16

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

A.

Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B.

Set up the requirement date manually as February 5.

C.

Set up the requirement date aligned with the activity start date and an offset of 5 days

D.

Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Full Access