Searching for workable clues to ace the APMG-International AgilePM-Practitioner Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s AgilePM-Practitioner PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 49

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying

controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

A.

Encourage the Marketing Director to attend the End of Timebox Review.

B.

Attend the next Daily Stand-up to raise an issue about the windows.

C.

Prepare a summary of progress against plan, for presentation at the review.

D.

Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

Full Access
Question # 50

The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to

simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was

potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a

customer financial transaction.

Answer the following question about the actions to be taken by each role.

Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,

select from Column 2 the role that should carry out the action.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1

    Advise how the legislation on the transfer of data will affect the requirements

and the system.

    Agree the changes needed to the corporate technical architecture with the

Architecture Angels IT support team.

    Ensure the information security vulnerability is communicated to the AA Head

Office IT Director.

    Evaluate the impact of proposed security controls on the business and decide

on the most suitable solution.

    Reprioritise the requirements on the Prioritised Requirements List associated

with the security issue.

Column 2

    Project Manager

    Business Sponsor

    Business Visionary

    Technical Coordinator

    Business Analyst

    Team Leader

    Business Ambassador

    Solution Developer

Full Access
Question # 51

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.

Is this an appropriate action related to acceptance criteria?

A.

Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox ' s deliverable as a whole, in order to keep focus on the business need.

B.

Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.

C.

No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements ' acceptance criteria, with nothing extra.

D.

No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.

Full Access
Question # 52

Using the additional information provided for this question in the Scenario Booklet, answer the following questions about the requirement for a fire exit from the

upstairs of the building.

What is an appropriate reason to classify the need for a secondary exit from the upstairs of the building as a Must Have requirement?

A.

Provision of a secondary exit from the upstairs of the building will ensure compliance with national fire safety regulations.

B.

A secondary exit from the upstairs of the building would help ease congestion in busy periods during festivals.

C.

A secondary exit from the upstairs of the building will provide a shorter and more direct route into the garden than the main stairway.

D.

The requirement for a secondary exit from the upstairs of the building has to be made a higher priority in order to be moved to an earlier Timebox.

Full Access
Question # 53

Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?

A.

Accustomed to bringing in contract staff for short periods of time.

B.

Closely manages the building team so that they consistently produce high-quality work.

C.

Is able to represent the team in all daily meetings.

D.

An experienced builder who is good at turning a brief into a practical design.

E.

Is empowered by Timber Tigers ' management to make decisions on the building work.

Full Access
Question # 54

During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent

any Planning Authority issues.

Is this an appropriate application of Agile Project Management for this project?

A.

Yes, because all stakeholders should attend the Daily Stand-up meetings.

B.

Yes, because each team member will have an opportunity to highlight any Planning Authority issues that may otherwise hinder their progress.

C.

No, because NOT all members of the Solution Development Team will attend the Daily Stand-up.

D.

No, because only members of the Solution Development Team should be permitted to attend Daily Stand-up meetings.

Full Access
Question # 55

What action should the Project Manager take during the Close-Out of Timebox C?

A.

Remove ' Aspects ' from the supplier list for all future projects.

B.

Carry out final checks to ensure the deliverables of Timebox C meet the expected standards.

C.

Ensure that lessons are learned so that similar issues do not occur in future Timeboxes.

D.

Initiate the work required to complete the windows to the required standard.